Total Baseline budget (BAC) for a project is Rs 50,000. Cumulative earned value (BCWP) to date is Rs 15,000. Cumulative actual cost (ACWP) to date is Rs 10,000. Assuming that conditions will not change, the cost database is reliable, budgeted cost of work completed to date (BCWP) and actual cost of work completed to date (ACWP) are cumulative, and past project progress is representative of future progress, calculate the final project cost forecast using the cost performance index.