A project will take a total of 720 person-days to complete. If the project must be completed in 30 days, how many people must be employed?

Respuesta :

Otras preguntas

Drew exercises every eight days and sara every 12 days. drew and sara both exercised today. how many days will it be until they exercise together again.?
A fair number cube with the numbers 1, 2, 3,4,5, and 6 is rolled what is the probability of getting an even number
Draw a bar diagram to represent 6 times more than $4
Marisa is counting wheels on bicycles and tricycles at the park. She coounted 3 vehicles and 7 wheels. How many bicycles and how many tricycles did Marisa see?
which of the following should you do to increase your reading rate?
This power enables the president to reject a bill passed by the legislature
at an amusement park a person spends $30 on admission and food and then goes on r number of rides that cost $2 each
can someone help me with all of these
math from 5th grade. it has a grid and says: number 100 times as much as 1/10 300 50 what do i put on 100 times as much and on the 1/10?? can s
Loom is to weaver as...