True of False: The difference between the cost baseline and the performance measurement baseline is: The cost baseline is the approved time-phased budget for the project showing all project costs except management reserves. When using earned value management, the cost baseline along with the scope and schedule baselines, become the performance measurement baseline. the point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.