1:Given the below cash flows for a project and a project WACC of 10%, what is the project’s NPV?
t FCFF
0 -150
1 50
2 100
3 200
2: Given the below cash flows for a project, what is its IRR?
t FCFF
0 -150
1 50
2 100
3 200