Patterson Co. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that a project's expected NPV can be negative, in which case it will be rejected.r: 10.00%Year 0 1 2 3Cash flows −$950 $500 $400 $300a. $54.62b. $57.49c. $60.52d. $63.54e. $66.72

Respuesta :

Answer:

NPV= $60.52

Explanation:

Giving the following information:

Robbins Inc. is considering a project that has the following cash flow: −$950 $500 $400 $300

Cost of capital= 10.00%

To calculate the net present value we need to use the following formula:

NPV= -Io + ∑[Cf/(1+i)^n]

Cf= cash flow

For example= Year 3: 300/1.10^3= 225.39

NPV= $60.52