When handling project scope creep, which are two things that all parties involved need to be aware of?

.Lowered expectations on project quality

.Separate accounts for new expectations

.Additional time needed for the project

.Additional resources needed for the project

Respuesta :

Additional resource needed for the projects

Additional time needed for the project

Explanation:

In any project handing their will expected diversion and add on requirement, so to complete a project additional time and additional resource is required to finish a project.

As advice due the project details, end user has keep enough buffer for deviations on resource of man power and additional times taken to finish the project.

While design the project each scope of work is measure with additional time to complete the task

Each scope of work is considered as task in project management.

Assuming alphabets A to D are assigned to the options, C and D will be the correct answers.

Scope Creep is a project management terminology that is used to describe a situation where due to imagined or real benefits, additional features become desirable for inclusion into or onto the project.

Inevitably, every product will require improvement. However, improvements, cannot continue within a project indefinitely because time, money, and other resources required to engage in such are limited or scarce. Improvements must be controlled.

Imagine that the next release of the iPhone is due by the end of March of 2022, the blueprint is finalized by September, 15th 2021. After the blueprint (which requires extensive research, deliberations, and consultation with engineers, supply chain managers who will ensure availability of the raw materials and resources needed,) is finalized, the most powerful member of the board then dreams up an idea and asks for the same to be incorporated.

Even before the project starts, there is bound to be loss of time and resources.

It is possible for these kinds of adjustments to be made even after the first prototype has been produced for testing. It is clear that this is not a very good situation for any company to be in. Besides the loss of time and resources, this can lead to burnout, disengagement, and ultimately the death of the project.

Some causes of Scope Creep are:

  • Internal miscommunication
  • Disagreements between project owner(s) and investor(s) or other parties
  • Variation between actual project and the requirement of the project owner
  • Lack of discipline
  • Poorly defined Project Scope

Learn more about Scope Creep here:

https://brainly.com/question/24369350