Answer:
                             January           February
Budgeted Material Cost          $65,450           $340,500
Explanation:
Direct materials budget for January and February .
                               January           February
Production                       1,950 units         2,110 units
Production Material needs (pounds) Â 9,750 Â Â Â Â Â Â Â Â Â Â Â Â 10,550
Add Budgeted Closing Materials     8,440              4,700
Total Materials needed             18,190             15,250
Less Budgeted Opening Materials   (5,100)             (8,440)
Budgeted Materials               13,090             6,810
Cost per material = $ 50 per pound
Budgeted Material Cost          $65,450           $340,500