Answer:
$12,240
Explanation:
For the computation of the amount of overhead first we need to find out the predetermined overhead rate which is shown below:-
Predetermined overhead rate = Overhead cost Ă· Machine hours
= $770,100 Ă· 1,510
= $510
Amount of overhead should be applied to Job 65A = Predetermined overhead rate Ă— Machine hours during January
= $510 Ă— 24
= $12,240
We simply applied the above formula