Respuesta :
Answer:
A. $8,187.17
B. $597.38
C. 30%
Explanation:
Calculate the Net Present Value of the Project at the Required Return of 9%
The following is the calculation of NPV using a financial calculator :
($8,000) Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
9.00 % Â Â i/yr
Shift NPV Â $8.187.1666 or $8,187.17
Calculate the Net Present Value of the Project at the Required Return of 9%
The following is the calculation of NPV using a financial calculator :
($8,000) Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
28.00 % Â Â i/yr
Shift NPV Â $597.3765 or $597.38
You will be indifferent between accepting the project and rejecting it at the internal rate of return. The Internal Rate of Return is the interest rate that makes the Present Vale of Cash Flows to equal the Initial Cost of the Investment.
Use the Data given to find the Internal Rate of Return :
($8,000) Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
$2,700 Â Â CFj
Shift IRR 30%