Answer:
$171,900
Explanation:
Davidson corporation manufactured 58,500 units during September
The first step is to calculate the fixed overhead machine cost per hour
= 170,520/3,480
= $48
The machine hours can be calculated as follows
= 3,480/58,000
= 0.06
The fixed overhead cost can be calculated as follows
= 0.06 × 49
= 2.94
Therefore the amount of fixed overhead that is allocated to production can be calculated as follows
= 58,500 × 2.94
= $171,900