Answer:
McMahon Corporation
Partial productivity measures for labor for the four locations:
                Mobile   Pecos   Spokane   Lansing
Labor productivity  3.26     3.93      3.29      2.48
(meals per labor
hour)
Explanation:
a) Data and Calculations:
                Mobile   Pecos   Spokane   Lansing  Total
Meals served     114,000  216,000   74,000    13,500  417,500
Labor-hours      35,000   55,000   22,500     5,250   117,750
Labor productivity  3.26     3.93       3.29      2.48    3.55
b) Labor productivity is computed as total output divided by labor-hours (labor input). Â It is the manpower or workforce productivity. Â It is one of the productivity measures with capital as the other measure.