32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the
same work by 16 workers working 8 hours per day?

Respuesta :

mhanifa
mhanifa mhanifa
  • 03-09-2021

Answer:

  • 45 days

Step-by-step explanation:

Total man hours:

  • 32*30*6 = 5760

Required days:

  • 5760/(16*8) = 45
Answer Link

Otras preguntas

Compare and contrast epidural and subdural hemorrhages.
The ancestors of elephants inhabited every continent except Antarctica and Australia. But the Asian and African elephants are the only ones to survive. Why? A.
Y=-3x+4. What is the y intercept?
A(n) _______ angle of a triangle is equal to the sum of the two remote interior angles. -Exterior -Interior -Complementary -Vertical
Find BC please in the picture
2 PONS Which situation is an example of an internal conflict? O A. A woman tries to get her company to change its policy regarding maternity leave. O B. A young
What were mojority of southern farmers
A marble is dropped from a height of 1m a. How long will the ball be in the air before it strikes the ground? b. What was the average velocity of the ball durin
Where is the insertion of the sartorius?
Through which duct can pancreatic juice be released into the small intestine without also releasing bile?