The Critical Path is B-D-E-G. See the definition of Critical Path below.
Critical Path refers to the order of steps that determines the shortest amount of time required for a task.
The Total Project completion time is 34 days. This is derived from the AON Network for the problem. See the attached.
AON (Activity - on -Node) diagram is a fundamental kind of logic diagram utilized for activity scheduling.
Slack time is the duration of a job that can be postponed without affecting other tasks or the project's completion deadline.
Hence, the slack time for EACH activity is given as follows:
A : 22-8 = 14
B : 0
C : 34 -19 = 15
D : 0
E : 0
F : 34-19 = 15
G : 0
Learn more about Critical Path at:
https://brainly.com/question/15091786
#SPJ1